Nchalo Water Supply Project

Project name: Upgrading and Extension of Nchalo Water Supply
Commencement date: 1 April 2024
Completion date: 30 April 2025
Contractor: Projex Group
Cost: MK 2,996,000,000.00
Project Components
•Intake at Illovo irrigation canals with 2No pumps abstracting raw water
•A pumping mainline of 350mm diameter ductile iron pipe
•A full conventional water treatment plant (15,762m³/Day capacity or 15,762,000 litres per day)
•An elevated steel tank of 500,000 litre capacity
•Sludge pond for water waste
•Security fencing.